Litigation, county facilities and cemetery policy top Chatham commissioners’ Oct. 5 agenda

By Chatham Journal staff

Pittsboro, NC – Chatham County commissioners will consider a four-phase government campus plan, weigh four options for replacing the county attorney and decide a contested Bear Creek business permit during an Oct. 5 special meeting that also includes a proposed cemetery-relocation policy and a park contract amendment funded by an engineering credit.

The board will meet Monday at 3 p.m. and again at 6 p.m. in the Historic Courthouse Courtroom in Pittsboro. Commissioners also plan a closed-session consultation on handling or settling ECO TIP West LLC v. Chatham County.

Several items carry specific implications. The facilities plan maps departmental relocations and future uses of existing buildings. The Bear Creek application follows a withdrawn heavy-industrial rezoning request and documented neighborhood opposition. The cemetery proposal sets notice, oversight and recording requirements for moving remains.

Chatham County Commissioners Karen Howard, Katie Kenlan, Amanda Robertson, Franklin Gomez Flores, and Mike Roberson. (photo by Gene Galin)

Renaissance Campus would consolidate county services

One of Monday’s most consequential items is approval of the Chatham County Space Needs Study and Master Plan prepared by Hobbs Architects and The Wooten Company.

The proposed Renaissance Campus would develop county-owned land along U.S. 64 West, with frontage on Renaissance Drive and Innovation Way, between Pittsboro and Siler City. The staff report describes an approximately 277-acre acquisition; the attached planning report identifies the subject tract as approximately 272.08 acres. That difference should be clarified as the project advances.

County staff describe increasing pressure on existing facilities, with many departments approaching or exceeding capacity. The proposed plan would accommodate at least 20 years of projected growth and organize relocations in phases.

The architects’ executive summary envisions two-story facilities with approximately 70,000 square feet of combined building footprint and approximately 140,000 square feet of gross space. A shared entrance plaza and lobby would connect administrative and public-service functions, with a large public meeting room near the entrance.

Administrative departments proposed for the first phase include the County Manager’s Office, Human Resources, Finance and Information Technology. The public-services group includes Tax, Register of Deeds, GIS, Environmental Health, Permits and Inspections, Watershed Protection, Planning, Parks and Recreation administration, the Visitors Bureau and Economic Development.

The programming narrative recommends placing frequently visited services and large meeting rooms on the ground floor. The arrangement would bring together offices now operating in separate locations, potentially changing where residents pay taxes, record documents, seek permits or meet with planning staff.

The report’s square-footage descriptions are not entirely consistent. Its site-planning narrative lists different building areas from those in the executive summary and programming section. The documents establish the proposed campus concept, but commissioners and designers still need to explain which figures will govern detailed design.

The first-phase site plan includes 449 parking spaces, pedestrian connections, a bus shelter, stormwater facilities, landscaping buffers and amenity areas. Future phases identify additional government buildings and possible community features, including an amphitheater, picnic shelters, food-truck areas and greenway connections.

A potential future sheriff’s facility is also shown. Those later-phase concepts should be distinguished from projects with approved construction budgets or established completion dates.

Utilities and traffic remain important campus questions

The campus report identifies infrastructure work that would be necessary to support development. Existing services include an eight-inch water main and a four-inch sanitary sewer force main along Renaissance Drive. The Emergency Operations and Communications Center currently uses an on-site septic system.

The plan says surrounding utility infrastructure has transferred to Tri-River Utilities and reports that no immediate system extensions or capacity upgrades were planned at the time of the study. It also identifies concerns about sewer capacity and a dead-end water line that could limit capacity and redundancy.

A wastewater analysis included in the report proposes phased improvements. The first phase would require a new pump station, a force main and a gravity sewer. Later phases would extend the gravity sewer network.

The analysis estimates $4.45 million for first-phase wastewater infrastructure. Its four-phase sewer program totals approximately $6.224 million, with four additional alternatives totaling approximately $2.08 million. Together, those estimates reach $8.304 million.

Those figures cover wastewater improvements. They are not the total cost of constructing the government campus, and the alternatives should not automatically be treated as a single approved package. They are planning estimates, subject to the decisions and engineering that follow.

The report also describes possible access from U.S. 64 near an existing median opening. A full-movement driveway would depend on a traffic impact analysis, with turn lanes or signals to be determined through that process.

Streams, riparian buffers, flood-hazard areas and uneven terrain also influence the site layout. The report proposes bridge structures for stream crossings and says building placement is intended to reduce grading and environmental disturbance.

County staff say approval would allow detailed design, engineering and construction planning to proceed. The agenda item does not itself establish a comprehensive construction appropriation or a firm campus opening date.

Plan would reshape use of downtown buildings

The facilities report reaches beyond the new site. It identifies buildings the county expects to retain, buildings that could expand and buildings that would become vacant after departmental relocations.

The County Annex, now housing the County Manager’s Office, Finance, Tax, GIS and Register of Deeds, would be vacated following the first-phase moves.

Information Technology would leave the old library at 158 West Street, and Tax Collection would leave the old bank building at 192 West Street.

The Historic Courthouse would remain a museum and public meeting space, while the Justice Center would continue serving court functions. Facilities operations would remain in the Performance Building after other departments move.

The Dunlap Building presents a different decision. Planning, Permits and Inspections, and Watershed Protection would relocate, while Public Health could remain and expand into available space or move to a possible health campus associated with the Department of Social Services site.

The report also discusses potential expansion at the Agricultural and Civil Center and Environmental Quality Building, additional library locations and future aging-services space. These are planning considerations with different levels of development.

For downtown Pittsboro, the eventual disposition of vacated buildings could become an important separate issue. Monday’s plan does not establish a sale, a redevelopment agreement or a new private use for those properties.

Four options for the next county attorney

The attorney-selection presentation has a specific trigger: the current county attorney is planning to transition out of the role.

Commissioners are being asked to receive a presentation, rather than make a scheduled final appointment. The attached slides identify four approaches and outline their advantages, costs and transition concerns.

The first option is to continue with Poyner Spruill LLP, the current firm. The presentation cites its familiarity with county operations and prior legal matters, established working relationships with staff and expertise across multiple areas. Selection under that approach would be limited to attorneys employed by the firm.

The second option is to solicit proposals from other law firms. A competitive process would allow comparison of services, fees and approaches, but would require time to prepare a request for proposals, evaluate responses and conduct interviews. A transition could also involve loss of institutional knowledge.

The third option is to hire a staff attorney who would serve as county attorney. That would provide full-time counsel dedicated to county operations. The presentation cautions that specialized outside counsel might still be necessary, potentially adding to costs.

The fourth is a hybrid arrangement: an internal staff attorney would support departments, contracts, policies and daily compliance, while an outside attorney on retainer would serve as county attorney. That would fund both salary and benefits for an employee and retained legal services.

The slides also describe the hybrid approach as a possible long-term transition toward an arrangement relying on a staff county attorney. There is no salary, retainer figure or detailed cost comparison provided in the presentation.

The presentation cites the statutory requirement that commissioners appoint a county attorney as their legal adviser and notes that the appointment must occur in open session. Monday’s discussion could establish a direction or selection process, but the materials do not name a successor.

ECO TIP consultation scheduled behind closed doors

The afternoon agenda contains two proposed closed sessions under North Carolina General Statute 143-318.11(a)(3), the attorney-client consultation provision.

The first is a general request to consult with retained counsel to preserve privilege. The second identifies ECO TIP West LLC v. Chatham County and authorizes consideration of the case’s “handling or settlement.”

The agenda records do not disclose a proposed settlement amount, negotiation terms or the advice commissioners expect to receive.

State law permits privileged attorney consultations and instructions concerning legal proceedings. It also requires settlement terms generally to be reported and entered in the public body’s minutes within a reasonable time after a settlement is concluded.

Bear Creek request follows withdrawn industrial rezoning

The evening session includes a special-use permit request from Lockley Holdings LLC for a contractor’s storage yard and staging area at 1656 Campbell Road in Bear Creek.

The proposal covers 3.9 acres within a 10.02-acre tract, Parcel 9390, and would support the adjacent Bear Creek Fabrications operation. The property would retain R-1 residential zoning, with the specified use authorized through a special-use permit.

The staff report explains that the applicant sought general-use heavy-industrial zoning for the entire parcel in 2025. Neighbors objected to the breadth of uses that could become available under that designation, and the applicant withdrew the request.

The current proposal narrows the requested approval to a storage and staging area on mostly cleared pasture. The applicant says additional space would improve organization and access to fabricated steel products without increasing production capacity.

The materials document continuing neighborhood objections. Staff report that five residents spoke against the permit at the June 15 evidentiary hearing, citing noise from steel handling and semi-trucks, traffic concerns and activity outside the business’s stated hours.

The report identifies concerns about a school-bus stop and truck movements at Campbell Road and Vernie Phillips Road. It also notes that alteration of the road intersection would be an N.C. Department of Transportation responsibility.

The applicant’s position is that the expanded staging area would reduce repeated handling of steel beams and thereby reduce noise. Proposed landscaping includes a dense Type A screen and a planted berm on the northern side. Directional signs would help truck drivers locate the existing entrance.

Access would use the established driveway serving the adjoining business, rather than a new entrance from Campbell Road. The application proposes no lighting in the staging area; directional signs would initially use reflective lettering.

Planning Board recommends approval, 7-2

The staff report says the Planning Board recommended approval by a 7-2 vote, with members identified as Lyons and Andrews opposing. It also references a minority report among the online application materials.

According to staff, expert witnesses testified that the permit would not harm surrounding property values or affect traffic conditions. Staff conclude that the application satisfies the five required findings.

The report also recounts Planning Board concerns about limits on additional testimony after the evidentiary hearing closed. Staff and the applicant’s attorney explained that the later review could not simply introduce new evidence into a closed record.

That procedural distinction matters for Monday. The permit is a quasi-judicial decision involving a defined evidentiary record, rather than an unrestricted policy debate in which every new comment becomes evidence.

The proposed approval resolution would require implementation of the Appearance Commission-reviewed landscaping plan and allow inspections to confirm that buffers are installed and healthy. Other conditions address required permits, compliance with approved plans and county authorization before changes.

Cemetery policy would establish notice and oversight

The final substantive item is a proposed Abandoned Cemetery Disinterment and Reinterment Policy, presented by Strategic Initiatives Manager Brenton Hart.

County staff say Chatham currently lacks a formal local policy assigning procedures and administrative responsibilities for such requests. The proposal would establish a framework under state law for unincorporated areas of the county.

The policy distinguishes applications by property owners or other parties from requests by next of kin. For applicants other than relatives, the Clerk to the Board would receive the application and review completeness with the Public Health Director.

If a burial site lies within municipal limits, the clerk would refer the application to the appropriate municipality, with the county retaining only supervisory functions assigned by law.

Applicants would have to give 30 days’ written notice to known next of kin, or relatives identifiable through reasonable search and inquiry. They would also publish notice weekly for four successive weeks in a newspaper of general circulation in Chatham County, beginning at least 30 days before the proposed disinterment.

Proof of notice would be required before the request is scheduled for commissioners’ consideration. For unmarked graves or indications of archaeological resources, the clerk would notify and consult the North Carolina Office of State Archaeology before scheduling the matter.

Applicants would pay relocation costs

The proposed cemetery policy would require a licensed funeral director to conduct the physical removal and reburial. Applicants would pay related expenses, including a new burial site, necessary coffins or boxes, and protection and replacement of markers.

The policy also calls for reimbursement of the actual reasonable expenses of one next of kin attending the disinterment and reinterment, capped at $200 under the cited statute.

A Public Health permit would follow board approval for applications requiring that approval. Within 30 days after completion, the applicant would file a Certificate of Removal Facts with the Register of Deeds, including the identities of the deceased when ascertainable and precise descriptions of the original and new burial locations.

Next-of-kin requests would follow a separate route without commissioners’ approval, while remaining subject to applicable law and Public Health permitting. The Public Health Director would have authority to stop active work for violations.

The policy expressly states that it confers no eminent-domain authority. Staff anticipate no significant budget impact because existing employees would handle administration and applicants would pay relocation expenses.

Monday’s vote concerns general procedures. It does not identify a particular cemetery for removal.

Pittsboro would build parking; county would maintain it

The Lewis Freeman Park parking agreement would place a gravel lot on county property at 192 West Street to serve the town park at 56 Rectory Street.

The proposed memorandum assigns design and construction costs and project management to Pittsboro. The town would obtain permits, oversee inspections, coordinate contractors and provide park-use signage.

Chatham County would retain final approval of placement and appearance and assume ongoing maintenance after completion. Improvements would become county property, with no ownership interest retained by the town.

The initial agreement would last five years, with one additional five-year renewal possible by mutual written agreement. Either government could terminate it with 180 days’ written notice.

Park amendment shifts engineering credit into contingency

Parker’s Ridge Park Change Order 003 would increase Frank L. Blum Construction’s Guaranteed Maximum Price by $55,249, from $8,338,878 to $8,394,127.

Staff describe a $55,249.50 credit from Stewart Engineering, the designer of record, and propose applying $55,249 to the construction contract. The change-order backup says the replenishment addresses owner contingency previously used for delay costs associated with permit approval and notice-to-proceed impacts.

Staff emphasize that the amendment “will not increase the overall cost of the project.” The change order adds zero days and lists substantial completion as June 15, 2027.

Transit, health funding and appointments round out consent

Commissioners will consider designating Chatham Transit Network to apply for Section 5311 assistance for fiscal years 2028 through 2032. The proposed resolution also authorizes required certifications and execution of grant and cooperative agreements. It identifies no award amount or new route.

An additional $2,081 in maternal-health funding would bring the fiscal 2027 agreement-addendum total to $25,495. Staff say it supports prenatal care and related services, with no local funding requested. The amendment requires an updated budget by Oct. 31 and services under the additional funding by May 31, 2027.

Two appointments would receive county approval: Philip Daniels as Pittsboro’s Parks and Recreation Advisory Board ETJ representative through June 30, 2028, and Cassandra Shirlle Lee as a Siler City Planning Board ETJ member through June 30, 2029. The linked Siler City correspondence spells Lee’s middle name differently, another detail to confirm in the final appointment record.

Library volunteers and veterans recognized

The afternoon opening includes proposed recognition of the Friends of the Chatham Community Library, Friends of Goldston and Friends of the Wren Memorial Library for fundraising, volunteer service, advocacy and support for library programs.

A second resolution would recognize Operation Green Light for Veterans from Nov. 2 through Nov. 11. It proposes green lighting at the Historic Courthouse and encourages residents, businesses and organizations to display green lights in support of veterans.

Monday’s decisions could advance a major facilities transition, establish direction for legal services and resolve a disputed rural business request. The cemetery proposal would create a documented process for an especially sensitive responsibility, while the consent agenda addresses ongoing services and intergovernmental obligations.